Substation 2022

132kV Grid Station — SITE Industrial Area

Complete EPC of a 132/11kV, 40 MVA grid station supplying power to 300+ industrial units in the SITE area.

AK SMARTECH delivered this landmark grid station project on a fast-track, 18-month schedule. The station features two 20 MVA power transformers, GIS switchgear, numerical protection relays, and a full SCADA/RTU system integrated with the K-Electric control center.

Key Achievements

  • Delivered 3 weeks ahead of schedule
  • Zero LTI (Lost Time Injuries) throughout construction
  • Seamless integration with existing K-Electric SCADA network